CHP Standard Installation Outline/Timeline


Below is a brief overview of the process of a "standard installation" (some jobs veer off of this and thus are no longer "standard" which will result in additional on-site charges). Please note that though the "Days" shown below are sequential, they are not always performed back to back, as there can be days off in between.


Week 1, Day 1 - CHP will meet with the homeowner on site & begin excavation with 1 load of pea-stone delivered to site. CHP will call the town to initiate the hole inspection (if applicable). Homeowner MUST have permit posted & accessible for inspector to sign

Week 1, Day 2 - Bring Pool to Site (all pools leave from CT between 10am-12pm)

Week 1, Day 3 - Level, Order Water & Partially Backfill with 2 loads of pea-stone (CHP orders water - homeowner required to pay trucking company on site)


Week 2 - POTENTIALLY A WEEK OFF WITH NO WORK TO BE DONE (depends on the time of year and current workload)

Week 2/3, Day 1 - Bring Pool Equipment to Site, Plumb Pool, & Dig Utility Trenches (40' included electrical & no sand, 10' gas with sand). All excavated material stays on site.

Week 2/3, Day 2 - Cont. Plumbing (for pool/spa combos only)

Week 2/3, Day 2 or 3 - Homeowner notifies Electrical & Gas Subcontractors to do hookups & get inspections


Week 3/4 - Homeowner notifies CHP when subcontractors are finished & inspected (pool pump must be hardwired, lights in conduit, and inspections passed already).


Week 3/4 or 5, Day 1 - CHP returns to backfill pool with up to 1 load of pea-stone and pour collar for pools with concrete decks only. Homeowner to assume pool water maintenance at this point.

Week 3/4 or 5, Day 2a (if applicable) - CHP returns to pour the collar if not able to pour at the time of backfilling (concrete patios only). Homeowner to assume pool water maintenance at this point.

Week 3/4 or 5, Day 2b (if applicable) - Homeowner notifies electrician that bonding grid can be placed

Week 3/4 or 5, Day 3 (if applicable) - Electrician gets bond grid inspected

Week 3/4 or 5, Day 4 (if applicable) - Homeowner notified CHP that grid passed inspection


Week 4/5 or 6, Day 1 - (if applicable) - CHP returns on additional day to pour collar for pools with paver decks. Homeowner to assume pool water maintenance at this point.


Week 6/7 - (if applicable) Automatic Cover tracks (aka "encapsulation") installed. Pools with auto covers must wait until this step has been completed prior to starting on any coping/patio work.

Week 6+ - Patio/Fencing constructed. Homeowner contacts CHP when ready for lesson (can be before or after patio). Homeowner is responsible to maintain pool water levels, salt/chlorine levels, cleans pump & skimmer baskets during this time.


Lessons - All installations come with an equipment lesson on site. This can be done before or after the patio has been installed. Homeowner to contact CHP when ready. Please allow 2-4 weeks for this to be scheduled.


Closing Permits - Homeowner notifies town to close permit. In some cases, CHP may need to call directly. If so, this is to be initiated by the homeowner at the request of the town. NOTE: all fencing must be in (including any door alarms) and electrical/gas permits closed prior to scheduling the final inspection.


Pool Covers & Winterizing - CHP will send out an email to all customers to schedule their first year complimentary pool closing & to begin the process of ordering winter covers. If a customer does not receive an email, it is advised that they contact CHP during the month of August for more information. Please note that patios need to be fully installed before ordering a winter cover.


Opening Pools - CHP will send out an email to all homeowners to schedule their first year complimentary opening during the month of March. If a customer does not receive an email, it is advised that they contact CHP for more information. After the pool has been opened, it is the customer's responsibility to begin maintaining the water chemistry. Please note that the complimentary pool opening is a single trip to remove the cover (if applicable), to start the equipment, and to add preliminary chemicals. Please note that after the complimentary opening, additional chemicals and maintenance will be necessary. This is now the homeowners responsibility as CHP is unable to make any return trips for pool maintenance.


MAINTANENCE - Cherry Hill does NOT do any pool water maintenance. After the pool has been installed, it is the homeowners responsibility to begin maintaining their water chemistry or to hire someone to do this for them. This holds true for the complimentary pool opening as well. Beyond the opening itself, all homeowners will need to begin treating their water as needed.